How to choose a PEB company in India: 10 checks before you sign
Most PEB disputes do not start on site. They start at the award, when two quotations that looked alike turn out to describe different buildings, or when nobody owns the gap between the steel and the civil work. These ten checks, in roughly the order you will meet them, help you pick a company you will still be glad you chose at handover.
1. Who designs the building?
Ask who does the structural design and to which codes. In India that means IS 800 for steel design and IS 875 for loads, including wind under Part 3. You should receive the design loads in writing: live load, wind speed, collateral load for services and solar, and crane loads if any. A company that quotes a weight without stating loads is quoting a guess.
2. Will you see drawings before fabrication?
You should approve general arrangement drawings, the anchor bolt plan and the main member sizes before cutting starts. Changes on paper cost nothing. Changes in steel cost money and time.
3. Where is the steel made?
Built-up frames are welded from plate on fabrication lines, and purlins and girts are roll-formed. Whether the company has its own plant or works with partner plants, ask which plant, and visit it if you can. Look for organised lines, marked pieces and a quality check before dispatch.
4. Material certificates
Ask for mill test certificates for the plates and coils used in your job, with the steel grade. For roof and wall sheeting, the quotation should state the base metal thickness (for example 0.50 mm TCT), the coating type and the coating mass, not just “colour-coated sheet”.
5. Welding and dimensional checks
Ask how welds and dimensions are checked: visual inspection, testing of critical welds where specified, and checks against shop drawings. Holes and end plates that are off by a few millimetres turn into days of rework on site.
6. Surface protection
Surface preparation and paint system should match the site: an inland dry site and a coastal or chemical environment need very different protection. The quotation should name the primer and finish coats and their dry film thickness.
7. Who erects it, and how safely?
Ask whether the company erects with its own riggers, fitters and supervisors or subcontracts the work, which cranes and lifting plans it uses, and how it manages safety: induction, harnesses and lifelines, and exclusion zones under lifts. A site accident stops your project, whoever is at fault.
8. Single-point responsibility
The most common site problem is anchor bolts that do not match the steel. When one company handles the steel design, fabrication, erection and civil work, the foundations are built to the same drawings as the frame, and there is one party to call if anything goes wrong. If you split the work, make the interface explicit: who sets the anchor bolts, to which drawing, and who checks them.
9. References you can visit
Ask for projects similar to yours in size and type, a crane building if you need cranes, and call or visit the owners. Ask how the company handled changes, delays and snags, not just whether the building is standing.
10. Scope, payments and handover
- Scope. Freight, unloading, cranes, sheeting accessories, gutters, doors, taxes, civil work: listed as included or excluded, line by line.
- Payments. Tied to milestones, such as drawing approval, dispatch and erection stages, not front-loaded.
- Handover. A snag list, final inspection, as-built drawings and maintenance guidance for paint, bolts and sheeting.
Red flags
| You see | It often means |
|---|---|
| Price far below the others | Lower design loads, thinner sheets or missing scope |
| Weight quoted, loads not stated | No real design behind the number |
| “Colour-coated sheet” with no thickness | Thinner sheet than you expect |
| Large advance, vague milestones | Little leverage if the work slips |
| No drawings until after the order | Changes will be costly |
How we work at Best PEB
Best PEB & Infrastructure has delivered more than 100 projects since 2017, with over 20,000 tonnes of steel work across more than 20 states, including metro station steel in Nagpur and Mumbai. We design to IS 800, share drawings for approval before fabrication, erect with our own riggers, fitters and supervisors under a safety induction programme, report progress daily with photos, and close every job with a snag list, inspection and handover. Our erection and civil teams work from the same drawings. See our projects.
The quickest way to compare companies fairly is to give them all the same brief. Build yours in the 3D designer and you get a design sheet with stated loads and a budget quotation to compare others against. Our guides on questions before a quote and PEB costs cover the rest.
Questions owners ask
What should I check before hiring a PEB company?
Who designs it and to which codes, whether you approve drawings before fabrication, material certificates and sheet specifications, welding and coating checks, who erects it and how safely, references, and a clear scope with milestone payments.
Is it better to give PEB steel and civil work to one company?
Usually, yes. One company building the foundations to the same drawings as the steel avoids the most common site problem, mismatched anchor bolts, and gives you one party responsible for the whole building.
Why are some PEB quotations much cheaper than others?
Usually because they are designed for lower loads, use thinner sheeting, or leave out items such as freight, erection, accessories or civil work. Ask every bidder for the design loads and a line-by-line scope.