Factory building with an EOT crane: what to plan before you build

By the Best PEB engineering team ·

In a factory with an overhead crane, the crane is not equipment you add to the building. It is one of the main loads the building is designed for. The crane decides the column sizes, the eave height, the bracing and the foundations, so it has to be settled before anything else. This guide walks through what to decide, in the order a structural designer needs it.

Why the crane comes first

A crane runs on rails carried by runway beams, which sit on brackets on the main columns. Every lift pushes down on those brackets, and every start, stop and trolley movement pushes the building sideways and along its length. A column that carries a crane is a different column from one that only holds up a roof. In our design engine, adding a 10 t crane to a 24 m wide factory added about a quarter to the steel weight. Our cost guide has more on what drives the steel weight.

1. Capacity: plan for the heaviest real lift

State the safe working load in tonnes, based on the heaviest item you will lift: a die, a coil, a machine for maintenance, a loaded mould. Add a margin if your products are likely to get heavier. Upgrading the crane later is easy. Upgrading the building that carries it is not.

2. Duty: how often and how hard it works

A crane used a few times a day for maintenance is very different from one running every shift at near full load. Indian practice classifies crane duty under IS 807 and IS 3177 by how often the crane works and how close to capacity. Heavier duty means more fatigue cycles on the runway beams and brackets. Tell your builder honestly how the crane will be used. If you already have a crane supplier, share their data sheet with the wheel loads.

3. Hook height sets the eave height

Owners usually know the hook height they need: the height to lift the tallest item over the tallest machine. The building has to fit three things above the floor:

  • Hook height at the highest hook position.
  • The crane itself: the height from the hook to the top of the rail, plus the crab above it.
  • Clearance between the top of the crane and the underside of the roof structure.

Get the crane dimensions from the supplier, because they differ between makes. A double-girder crane usually gives more hook height for the same building height than a single-girder one.

4. Crane span and building span

The crane span is measured between rail centres, so it is a little less than the building width. The crane also cannot reach right up to the walls, so leave space along the sides and ends that the hook will not cover, and keep machines that need lifting away from those strips. Manufacturers generally recommend a double-girder crane for heavier capacities, longer spans or more continuous duty.

5. Runway beams, brackets and bracing

  • Runway beams (gantry girders) carry the rails along the length of the building and are sized for wheel loads, impact and fatigue.
  • Brackets on the main columns carry the runway beams. For heavier cranes, a stepped or separate crane column is often better than a bracket.
  • Crane stops at the ends of the runway, and rail clips that allow the rail to be aligned.
  • Longitudinal bracing in the crane bays carries the braking forces along the building down to the foundations.

The deflection of the runway beams matters as much as their strength. A beam that sags or sways too much makes the crane crab-walk and wears out wheels and rails.

6. Foundations

Crane columns deliver larger and more varied loads to the ground, including sideways forces at every move. The footings, pedestals and anchor bolts must be designed for them. Ask for a soil investigation before design, and make sure the civil work and the steel are designed together. Our civil team builds the footings to the steel designer’s reactions for exactly this reason.

Planning a crane for later?

If you will install the crane in two or three years, design the building for it now. Add the brackets, size the columns and footings, and leave the runway beams for later. Strengthening a finished building for a crane costs far more than designing for it from the start, and sometimes it is not practical at all.

What to give your PEB builder

Information Why it matters
Capacity (t) and number of cranes Sets the column, bracket and foundation design
Duty: how often, how heavy Sets the fatigue design of the runway
Hook height needed Sets the eave height
Which bays the crane covers Runway length, end stops and bracing
Crane make or data sheet, if chosen Exact wheel loads and clearances
Future cranes or upgrades Design once instead of strengthening later

Try it in 3D

Our 3D designer opens with a factory and crane preset. Set the size and height and choose a crane, from 3 t to 20 t. Our engineers send back a design sheet and a budget quotation based on the calculated steel. See also PEB factory buildings and our checklist of questions to settle before a quote.

Questions owners ask

Can an EOT crane be added to an existing PEB building?

Only if the building was designed for it. Otherwise the columns, connections, bracing and foundations usually need strengthening, which can cost more than designing for the crane at the start. If you plan a crane later, include it in the design now.

How is the eave height worked out for a crane building?

Start from the hook height you need, add the height of the crane from hook to rail and the crab above it, then leave clearance under the roof structure. Crane makers publish these dimensions for each model.

Single girder or double girder EOT crane?

Single girder cranes suit lighter loads and shorter spans. Manufacturers generally recommend double girder cranes for heavier capacities, longer spans, more hook height or continuous heavy duty.